NEW DELHI: A district consumer commission in Delhi has directed Eicher Motors (Royal Enfield) and Shree Mahadev Motors, its authorised dealer, to jointly pay Rs 1 lakh to a Noida man whose Interceptor 650 motorcycle lost power at high altitudes during a Leh trip. The commission found that the complainant’s allegations stood unrebutted and that compensation was justified.

Why did the Royal Enfield bike lose power during the Leh trip?

The complainant, Hasan Murtaza, had purchased a Royal Enfield Interceptor 650 from Ess Aar Motors on April 13, 2019. He alleged that shortly after the purchase, the bike developed an Electronic Control Unit (ECU) problem that caused loss of power at higher altitudes, as per the commission order.Royal Enfield later introduced a 30-minute software update to address the problem, available free of cost to customers who had purchased the motorcycle between November 2018 and May 2019.Having planned a Leh trip in May 2021, Murtaza gave the bike to Shree Mahadev Motors in June 2021 and, he alleged, specifically asked the dealer to update the ECU. He claimed he was informed at the time of delivery that the update had been completed and the motorcycle was ready for higher altitudes.However, during the trip, the bike lost power at an elevation of 15,912 feet. Murtaza alleged that he had to drag the motorcycle and faced extreme difficulty travelling in the high-altitude terrain.After reaching Leh on September 21, 2021, he took the bike to an authorised Royal Enfield service centre the next day. He was allegedly told that the ECU had never been updated and the centre did not have the necessary equipment. He was also asked to wait a few weeks for a replacement part.Murtaza later alleged that the dealer initially claimed the update had been completed but retracted its statement when confronted with the service centre’s findings. He alleged that he had no option but to leave the bike at a hotel in Leh, and later rode it back to Noida, facing similar problems.

What did the commission say?

The bench comprising President Monika A Srivastava and member Kiran Kaushal noted that the complainant had produced the purchase invoice, correspondence with the companies and evidence of his Leh trip. It also took note of the emails exchanged with the companies and the absence of any documentary evidence showing that corrective measures had been taken to address the motorcycle’s ECU problem.The commission observed that Shree Mahadev Motors did not appear before it despite receiving notice and failed to file a reply. The right of the opposite parties to file a reply was also closed as it was beyond time. It said the complainant’s allegations remained unchallenged and there was no contradiction in the evidence relating to his Leh trip or his visit to the authorised service centre.“Despite notice OP-3 did not come to the Commission and neither filed any reply. The averments made by the complainant stand unrebutted and uncontroverted. There is no contradiction relating to the trip of the complainant to Leh. Complainant has placed on record the emails clarifying the authorized service centre visited by him at Leh and the date of his visit,” the commission observed.It further noted that no document had been produced to show that Eicher Motors had taken action against Shree Mahadev Motors over the complainant’s grievance. Finding no contradiction in the evidence submitted by Murtaza, the commission held that compensation was justified.“Therefore, this Commission is of the opinion that ends of justice would be met by directing OP-1 and OP-3 to jointly and severally pay a sum of Rs.1,00,000/- to the complainant,” the commission noted.

Final order

Announced on November 4, 2026, the commission directed:

  • Eicher Motors (Royal Enfield) and Shree Mahadev Motors to jointly and severally pay Rs 1 lakh as compensation to Murtaza.
  • The amount must be paid within three months of the order’s pronouncement.
  • In case of non-compliance, the companies will have to pay 6 percent annual interest from the date of the order until realisation.